This year we are raising money to“Depave” the back border of the playground and replace it with landscaped pathways, benches, 20 trees, and plants.

Next we will replace the swing with a new piece of playground equipment and repair and improve the tree mounds around the play structure.

The final phase will include the installation of a student created mural on the asphalt and repaint the futsal and baseball fields.




Interested in Donating? Click Here

Rather pay by check? Send checks made out to ASTOR PTSO to:

Astor School PTSO

5601 N Yale Avenue

Portland, OR 97203

Be sure to note PLAYGROUND PROJECT in the memo!

Donors who contribute $500 (or ten monthly payments of $50) or more, will be displayed, with gratitude, permanently on the playground.

Playground Plans

Depave and Planting Schedule

April 17th, Friday : Line Drawing

April 18th, Saturday: Cutting Asphalt

April 19th, Sunday: Cutting Asphalt

May 9th, Saturday, 10-2: Depave Day One (100 volunteers)

May 11th, Monday: Fencing Goes Up

May 30th, Saturday, 10-2: Depave Day Two (100 volunteers)

June: Excavation and Drop Boxes

Summer: Fencing Stays Up, Landscaping

October/November: Friends of Trees Planting Event/Verde Landscaping